This programme is intended for use with each measuring run of 10 or 15 minutes as recommended at "HOW TO GROUT
A HOLE" in the menu at right of screen
The programme gives the quantity of cement injected in each run calculated on the basis of the volume of grout
used from the agitator in the run.
The sketch shows typical grouting of a foundation. This comprises a number of measuring runs. For simplicity
only one drawdown in the agitator is shown; in many actual jobs the agitator needs to be topped-up several times
during grouting of a hole.
WATER : CEMENT ratio (by vol)=
: 1
Volume of grout taken = Cubic Feet
After entering these details, click on the CALCULATE button.
The amount of cement in this volume of grout is:
CEMENT= Pounds
HOWEVER
If a Report Form is used it provides an alternative to the use of this programme. It provides for the recording of
the grout left in the agitator at the end of each run and automatically calculates the cement used and totals it up.
Links to Report Forms are provided in the menu in the right hand column of the screen under the heading
"DOCUMENTING".